Campbell Elementary


Last Updated on 11-15-09
 Elevation      Plans


PROJECT SUMMARY:  There are two projects at Campbell Elementary:
 
1.     Campbell Elementary School Boiler Replacement (completed in 2007)
2.     Campbell Elementary School General Upgrades (completed in 2009)

Work was completed in September 2009 on the bond funded improvements.  Work included: general classroom upgrades, renovated restrooms, major renovation of the kitchen, replacement of classroom furnaces, bleachers in the gym, drainage and safety cushioning upgrades to the play equipment areas.
 

 
Campbell Elementary School Renovations and Improvements:


PROJECT SUMMARY: 

Work has been complete for bond funded improvements.  Work included: carpet replacement, paiting, new white boards, new clocks, renovated restrooms, replacement of south facing windows, air conditioning in technology lab, gym bleachers, and site improvements.

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, North Clackamas School District
 Project Manager:  Jon Sandstrom, J.J. Henri Co., Inc.
Architect:  Barrentine, Bates and Lee


PROJECT SCHEDULE:
Start Construction: June 2009
 Completion Date:  Sept. 2009

PROJECT SCHEDULE
 


UPCOMING ACTIVITIES:
  •   All bond funded work completed at Campbell Elementary in September, 2009.

PROJECT PHOTOS:
     
Play Area 8/09 Play Area 8/09 Office 8/09
New VCT in Hallway 8/09 Rebuilt Wall w/ Windows 8/09 Outside Rebuilt Wall w/ Windows 8/09
New Kitchen Equipment 8/09 New Kitchen Equipment 8/09 New Classroom Carpeting 8/09
Patio:  Failing Concrete Squares Replaced 7/09
Patio: Concrete Squares Replaced 7/09
Patio Replacement 7/09
Play Area Gravel Being Spread 7/09 Upper Play Area Improvements 7/09 Office Exterior Wall Replaced  7/09
Office Exterior Wall Replaced 7/09 Office 7/09 Office 7/09
New Wall 7/09
Sheet Rock work in Kitchen 7/09
Sheet Rock Work in Kitchen 7/09
Exposed Pipe in Classroom 7/09 Exposed Pipe in Classroom 7/09 Exposed Pipe in Classroom 7/09
 
 Campbell Elementary School Boiler Replacement Project:

PROJECT TEAM:  
Capital Proects Manager: Garry Kryszak, North Clackamas School District
 Project Manager: Dan Golden
Architect:  
Contractor:  TBD
Engineer:  SDC



PROJECT SCHEDULE:
Start Construction June 25, 2007
 Move In Date: N/A
Completion Date: August 31, 2007 

PROJECT SCHEDULE
 


UPCOMING ACTIVITIES :
  • Completed
 

PROJECT PHOTOS: