February 2007Meeting Schedule: Leslie Robinette Schedule for future meetings: 3rd Wednesdays — quarterly, with some additional as needed. If you have questions or hear questions raised by others, please e-mail them Leslie Robinette, who will track down the information you need. This will help us build an agenda for future meetings. With your permission, contact information for each committee member will be posted on the school district web site so the public can contact you directly with questions or concerns. Purpose of the Citizens Oversight Committee: Ron Naso
Question: Will there be a formal trade-off process for changes in the plan? Staff Roles: Ron Naso Ron Naso, Superintendent Joe Krumm, Director of Community & Government Relations Leslie Robinette, Communication Specialist Elaine Drakulich, Assistant Superintendent for Administrative Services Ron Stewart, Physical Plant Director Garry Kryszak, Bond Capital Project Manager Jim Langstraat, Executive Director for Finance and Operations Diane Larson, Director of Fiscal Services Tim Witcher, Director of Business Operations Matt Utterback, Director of Secondary Support Services Blair Loudat, Director of Technology and Information Services Bond Background: Ron Naso
Financial Report: Jim Langstraat
Planned Projects: Ron Stewart and Garry Kryszak
Schedule: Ron Stewart and Garry Kryszak
These are now in final stages of design, with zoning changes needed and site variance requests underway. We will use the CMGC (Construction Manager/General Contractor) design process in which a general contractor works with the architect in final design phase.
Happy Valley Elementary will be ready in the fall of 2008. The Happy Valley middle school will be ready in the fall of 2009. Architect assignments for major projects: Ron Steward and Garry Kryszak
The Ardenwald project kickoff with Mahlum architects will take place next week. The replacement school must be designed to be built while the old building is in operation. Much of the preliminary work with architects is now underway. (Walk throughs, planning, etc.) The big project push (many projects) will be in the summer of 2008. Quality is paramount: we have revised operational specifications that state our preferences for products, consistency, terminology, design specs, and quality. The architects are highly experienced and we have worked with many of them before. We will do $81 million in 2008 and $71 million in 2009. This is the most aggressive bond implementation plan in Oregon history. Good planning is as much work as good construction. Though you may not see a lot happening right now, there is a lot going on behind the scenes. Question: what accountability measures do we have for construction groups? Question: Why is it necessary to hire so many architects? We do try to have a standardized approach to our schools. Our elementary schools will look very much like those at Spring Mountain and Oregon Trail. We have hired 3 project management firms: Milstead & Associates, J.J. Henry, and Cornerstone. Project management costs are built into the reserve fund. Question: Are there performance benchmarks for the project managers? Question: Will there be any recovery of capital in the teardown of an old school? Land Acquisition: Tim Witcher Realtor Tom Dechenne of the Norris Beggs & Simpson commercial real estate firm has been working with the district since spring 2006. We have been trying to position ourselves to negotiate for real estate since before the bond was approved. Our focus is on the east side of the district, within the Urban Growth boundary. We have been searching for sites large enough for schools. Who is interested in selling? Uncertainty arises because the zoning is not set and therefore the prices are not set. We have looked at a large number of properties with the district’s location goals in mind. Goal: 10 acres for a grade school, 30-40 acres for a middle school (eventual high school). Sites were reviewed by members of the Site Committee. General areas were targeted. Some properties have been weeded out due to physical constraints such as wetlands, creeks, etc. Appraisals have been ordered for the district to purchase property at fair market value. These should be ready in a week or two. We are prepared to make offers, though we are still narrowing down our choices. No offers have been made yet. Much of the property was originally zoned as farmland and has not yet been re-zoned. Between 162nd & 172nd is where we need sites for two new elementary schools and the new middle school that will eventually become a high school. The district is also seeking pieces of property for future schools east of 172nd. The school district extends to 180th Ave. Because of planned growth in Damascus (part of which lies in our district), we need to look at sites for future schools on the far eastern edge of the district. Question: What about the Altamont property? Question: What about the property next to Rowe Middle School? Athletic Facilities: Ron Naso There is $3 million in the bond for athletic facilities. We are trying to parlay the 3 million in athletic funding into 4.2 million through partnerships. All-weather surfaces for our 3 high schools, will be accomplished in partnership with other agencies or community groups. Parks & Recreation is discussing this with us. Ron Naso is confident that within 2 years we will have all-weather surfaces at all 3 high schools. CHS has the stadium and lights in place, so it is ready to move forward now. The community is eager to move forward with this. City of HV has an agreement with Parks and Recreation to contribute a certain amount of facilities within Happy Valley. This specifically requires an all-weather surface within the City of Happy Valley. We are discussing whether it would make better sense from a land and economic standpoint to merge their field with our field, rather than creating two fields. However, our high school does not lie within the boundaries of Happy Valley. We have requested that Happy Valley annex the high school site through “cherry stemming.” This has been controversial in parts of the community. Whether or not this happens, we have indications that there may still be a way to make this project work. We have scheduled installation of the all-weather surface at CHS this summer. At the other two high school fields, we are planning a number of other facilities improvements, seeking parity between schools.
Both of these high schools will also receive an all weather surface. Parks and Recreation has agreed to be a partner in both Milwaukie and Putnam. The District will provide $700,000 per school at both PHS and MHS. The target date for installation is the summer of 2008. Our commitment is to have parity at each high school. The new middle school site will have a track, but not a stadium until a later bond is passed to transform it into a high school. We are working closely with Parks & Recreation to find adjacent property parcels so we can make efficient use of greenspace. We are trying to find ways that schools can be built on smaller plots of land. Closing Remarks: Implementing the bond will be a messy process. Things will not always go as planned. Commitment for future meetings: 3rd Wednesdays as scheduled Next meeting is tentatively set for March 21 Meetings will run from 6:30 to 9 p.m. |