Clackamas Elementary


Last Updated on 9-18-08
PROJECT SUMMARY:
The Clackamas Elementary School has two projects:
 
1. Building Improvements
2. Roofing Project 
 
Building Improvements:

PROJECT SUMMARY:

Bourke Construction has been awarded a contract for painting and remodel work at Clackamas Elememtary. The remodels include a new study area and restroom upgrades throughout the school. Several other contractors are also working on smaller projects at Clackamas Elementary. These include drainage improvements for the site and a building card  access system.
 
PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Jon Sandstrom, J.J. Henri Co., Inc.
 Architect:  BBL
 Contractor: Bourke Construction
 Engineer:  N/A

PROJECT SCHEDULE:
 Start Construction:  June 2008
 Construction Complete: Sept. 2008

PROJECT SCHEDULE
 


UPCOMING ACTIVITIES :
  • This project was completed during the Summer of 2008.

PROJECT PHOTOS:
     
 New Trees and Plants
New Sidewalks
 Reading Alcove
 
Tile New Woodchips and Rubberized Padding Concrete Sidewalks
   

 Asphalt Drainage  

Daycare Painting

Handicap Parking

Main Hallway Painting Daycare Painting Classroom Painting

Wall Covering Abatement

Unit Ventilation Demo

Bathroom Demo

 
 
 
 




































































Roofing Project:
Clackamas Elementary Roofing project was completed during the summer of 2007. 

PROJECT TEAM:
Capital Projects Manager: Garry Kryszak
Project Manager: Tony Walters, Milestead & Associates
Architect: Barrentine, Bates & Lee
Contractor: First Aide Corp.
Engineer: N/A


PROJECT SCHEDULE:
Start Construction: June 20, 2007
Completoin Date: August 31, 2007

PROJECT SCHEDULE
 


UPCOMING ACTIVITIES:
  • This project was completed during the Summer of 2007.