Happy Valley Elementary School


Last Updated on 9-30-09

PROJECT SUMMARY:

The Happy Valley Elementary School / Middle School Project has been constructed on a 22 acre site adjacent to the previous Happy Valley Elementary School at 13865 SE King Rd., Happy Valley, OR 97086.  The previous school building remained in operation during the initial construction of the new facilities.  The new building is a total of 186,000 SF, including approximately 69,000 SF for the Elementary School and 117,000 SF for the Middle School.  The Elementary School (Kindergarten through 6th Grade) will accommodate 550 students, while the Middle School (7thth Grades) will accommodate 750 students.  Although the Elementary School & Middle School are adjoining within a single large structure, they will function as separate institutions.

Construction progress will be made simultaneously on both the Elementary School and Middle School portions of the building, but construction of the new Elementary School advanced more rapidly.   This enabled it to be put into operation for the start of the 2008-2009 school year.  The Middle School construction will be completed during the latter part of 2008. The Middle School will not be occupied as a Middle School until the 2009-2010 school year. Until that time, the new Middle School will be occupied by elementary students upon completion. 

 At the end of the 2007-2008 school year, the previous Elementary School was demolished.  Part of the overall program for this project is the construction of additional athletic fields and parking facilities at the site of the previous Elementary School.



 
 

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, North Clackamas School District
 Project Manager: Ron Blaj, J.J. Henri Co., Inc.
 Architect:  Boora
 Contractor: (CM/GC)  Emerick Construction
 Engineer:  N/A



PROJECT SCHEDULE:
Overall Construction Schedule: June 2007 – December 2008
New Elementary School Construction: Completed – August 2008
New Middle School Construction: June 2007 – November 2008
Demolition of Existing Elementary School: Completed – July 2008
Construction of Athletic Fields: August 2008 – October 2008

PROJECT SCHEDULE
 

Upcoming Activities: 
  • Elementary School portion of the building has been completed.
  • Repair of punch list items continues.
  • See Happy Valley Middle School report for activities that continue on the middle school portion of the building.

PROJECT PHOTOS:

   
Sign Playground
Elementary School Office Elementary School Planter
   
 Playground  Sign
 Principal  Sign
 Entrance and Drop Lights
 Elevator Door
 Landscaping  Corridor to Media Center
 Hot Water for Kitchen
 Skylights
 Eastside Bio Swale
Gym

New Bench

Driveway Bollards

Ariel 6/2008 NW Corner of Elementary School 5/2008
Interior Courtyard of Elementary School House 5/2008

Interior Courtyard of Elementary School 5/2008

Interior Work in Regular Size Elementary Classroom

 

Interior Work in Partitioned Classroom

 

 

 Panoramic View of Happy Valley Elementary School and MIddle School Site

 

        
 

King Road Electric Underground

 

 
   
   Front Wall Conduit