Infrastructure




  Elevation      Plans

Last Updated on 3-5-10

PROJECT SUMMARY:
:
The following general infrastructure improvements have been funded via the bond:

  • Upgrade of all District Building Security Alarm Systems. Systems installed and operational at all but
  1. Elementary Schools Concord, Riverside (scheduled for 2010)
  2. Alder Creek and Sunrise Middle Schools (scheduled for 2010)
  • Upgrade of fire alarm systems at 13 District Sites – completed at all sites except
  1. Elementary Schools Concord, Riverside and Sojourner (scheduled for 2010)
  • Upgrade of clock and bell systems - completed at all sites except
  1. Elementary Schools Concord, Riverside, Oak Grove and Sojourner (scheduled for 2010)
  2. Alder Creek Middle School (scheduled for 2010)
  • Installation of drainage and safety cushioning systems at all Elementary Schools – Completed at all schools except Concord, Riverside, Oak Grove and Sojourner (scheduled for 2010)

UPCOMING ACTIVITIES:

  • Upgrade Security Alarms - Concord, Riverside and Alder Creek - Summer of 2010
  • Upgrade Fire Alarms – Concord, Riverside, Sojourner and Alder Creek – Summer 2010
  • Upgrade Clock and Bell Systems – Concord, Riverside, Sojourner, Oak Grove and Alder Creek – Summer 2010
  • Upgrade of Play Equipment Areas – Concord, Oak Grove, Riverside and Sojourner - Summer 2010


PROJECT TEAM:
Capital Project Manager:  
 Project Manager:  
 Architect:  
 Contractor:  
 Engineer:  

 
PROJECT SCHEDULE:
   
   
   
   
   
 


PROJECT PHOTOS: