PROJECT SUMMARY:

  • A new bus drop off area has been constructed along Linwood Ave.
  • Office was completely remodeled and expanded
  • New lobby and enclosed hallways on the west and east side of bldg. were constructed
  • Old media center was remodeled into two resource rooms
  • All classrooms received new carpeting, heating upgrades, and dry marker boards
  • Hallway flooring upgraded and new tack board installed
  • Clocks were replaced throughout the building and intercom was replaced
  • New media center was completed in January  2009
  • New gym completed in April 2009
  • New store room for kitchen was constructed
  • Security system was upgraded
  • Site was fenced for security
  • New courtyard was constructed

 

 

 

PROJECT TEAM:
Capital Projects Manager: Garry Kryszak
 Project Manager:  Jerry Milstead, Milstead & Associates
 Architect:  BB & L
 Contractor: P & C Construction



PROJECT SCHEDULE:
Start Construction: June, 2008
 Completion Date: April, 2009

PROJECT SCHEDULE
 

UPCOMING ACTIVITIES:


  • Project Complete.

 

PROJECT PHOTOS:
   
West Side Media Center 5/09
Main Entrance 5/09
Linwood Bus Exit 5/09 Linwood Gym 5/09
New Main Entry 11/08 Inside Gym 11/08
New Classroom 10/08 New Curb 10/08
New Gym 10/08 Play Equipment 10/08











New Gym Panels 9/08 East End at Linwood Street 9/08
New Gym 9/08 New Gym Panels 9/08
New Admin Entrance 9/08 New Class Room Pod 9/08
North End of Bus Loop - Aug. 2008 New Bus Loop - Aug. 2008

East Classroom - Aug. 2008

West Outside Corridor - Aug. 2008