Milwaukie Elementary/El Puente


Last Updated on 9-30-09

PROJECT SUMMARY:  There are two projects for the Milwaukie/El Puente School.
 
1.  Milwaukie Elementary Roofing Project (completed in 2007)
2.  Milwaukie Elementary Building Improvements (completed 2009)

Building Improvements:
Work completed on bond funded improvements.  Work included: general upgrades in classrooms, replacement of old windows, security system upgrades, replacement of gym floor and play area upgrades.


PROJECT TEAM:
Capital Projects Manager: Garry Kryszak, North Clackamas School District
Project Manager:  Jon Sandstrom, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates & Lee


PROJECT SCHEDULE:
Construction Start: June 2009
 Completion:  August 2009

PROJECT SCHEDULE
 

UPCOMING ACTIVITIES:
  • All bond funded work completed September, 2009.

PROJECT PHOTOS:

 

 New Gym Floor 8/09
 New Gym Floor 8/09
New Windows 8/09
Tunnels under floor, showing steam pipes 7/09 Air Tube for Steam Pipes 7/09 Tunnels under floor 7/09
 Existing location of columns in play area 7/09
 New Footings will be placed play area 7/09
Basement  Demo 7/09 
Play area w/ new curb 7/09 Hallway: Carpet stripped off 7/09 Gym Floor being removed 7/09
 Gym floor being removed 7/09
 Flooring from Gym 7/09
 Carpet and subfloor removed in classroom 7/09


Roofing Project:
The Milwaukie Elementary School/El Puente Roofing project was completed during the summer of 2007.


PROJECT TEAM:
Capital Projects Manager: Garry Kryszak, North Clackamas School District
Project Manager: Tony Walters, Milestead & Associates
 Architect:  BB&L
Contractor: McDonald, Snyder, ABC Griffith


PROJECT SCHEDULE:
Construction Start: June 20, 2007
 Completion:  August 31, 2007

PROJECT SCHEDULE
 

UPCOMING ACTIVITIES:
  • The roofing project is complete.

PROJECT PHOTOS: