Oak Grove Elementary

 Last Updated on 7-15-10

  

There are two projects at Oak Grove Elementary:

1. Bus Lane Exit
2. Site Improvements/Renovations

BUS LANE EXIT

PROJECT SUMMARY:

Construct a new bus exit lane to Courtney Ave.  This project allowed for separation of bus and parent pick-up traffic improving safety and speeding up traffic flow.  The new lane will be for bus exiting only was completed in September, 2008.

PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas  School District
 Project Manager:  Dan Golden
 Architect:  N/A
 Contractor:  
 Engineer:  Compass Engineering

 
PROJECT SCHEDULE:
  Construction Start: June, 2008
  Completion Date: August, 2008
 
UPCOMING EVENTS:
  • Project completed.  Buses began using the new exit to Courtney Ave. on November 3, 2008.



PROJECT PHOTOS:

   


SITE IMPROVEMENTS

PROJECT SUMMARY:

Skyward Construction started work on June 21, 2010.  Asbestos tile have been removed from the cafeteria, foundations have been dug for the expansion of the covered play area.  Work has started on interior painting.

Work scheduled to be completed by August 28, 2010 includes interior painting, new bleachers in the gym, window glass replacement in selected rooms, new flooring in the cafeteria, and expansion of the covered play area.

Play equipment drainage and safety cushioning upgrades are also underway.


PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas  School District
 Project Manager: Joanna Evenson, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates and Lee
 Contractor:  Skyward Construction

 
PROJECT SCHEDULE:
  Construction Start: June 2010  
  Completion Date:   Aug.  2010
 

UPCOMING EVENTS:


PROJECT PHOTOS: