Oak Grove Elementary

 Last Updated on 4-27-11  

There are two projects at Oak Grove Elementary:

1. Site Improvement/Renovations
2. Bus Lane Exit

SITE IMPROVEMENTS

PROJECT SUMMARY:

 Skyward Construction completed work in October 2010 that included: Replacement of floor tile in the cafeteria, expansion of the coovered play area, interior painting, window glass replacement in selected rooms, gym floor refinishing, new bleachers in the gym, rest room finish upgrades and minor electrical upgrades.

In seperate project upgrades to the play equipment area were completed in August 201 and irrigation upgrades in the playfield were completed in December 2010.


PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas  School District
 Project Manager: Joanna Evenson, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates and Lee
 Contractor:  Skyward Construction

 
PROJECT SCHEDULE:
  Construction Start: June 2010  
  Completion Date:   Aug.  2010
 

UPCOMING EVENTS:
Projects complete. All bond related work at Oak Grove Elementary has been completed.

PROJECT PHOTOS:
     
   New Cafeteria Floor 8/10
 Playground 8/10
 
Covered Play Area Expansion 8/10
Playground Swings 8/10
 Restroom Upgrades 8/10
     


BUS LANE EXIT

PROJECT SUMMARY:

Construct a new bus exit lane to Courtney Ave.  This project allowed for separation of bus and parent pick-up traffic improving safety and speeding up traffic flow.  The new lane will be for bus exiting only was completed in September, 2008.

PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas  School District
 Project Manager:  Dan Golden
 Architect:  N/A
 Engineer:  Compass Engineering

 
PROJECT SCHEDULE:
  Construction Start: June, 2008
  Completion Date: August, 2008
 
UPCOMING EVENTS:
  • Project completed.  Buses began using the new exit to Courtney Ave. on November 3, 2008.



PROJECT PHOTOS: