Riverside Elementary


Last Updated on 11-15-09

PROJECT SUMMARY:

 There are three projects at Riverside Elementary:

1.   Building Improvements
2.   Boiler Replacement
3.   Roofing Project
 
 Riverside Elementary School Building Improvements:
PROJECT SUMMARY:

Bond funded improvements at Riverside Elementary are scheduled for the summer of 2010.  Work will include: painting, selected window replacement, repairs to covered play area, play equipment area drainage, upgrades to clock system, pavement upgrades.

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Joanna Evenson, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates and Lee
 Contractor:  TBD
 Engineer:  TBD


PROJECT SCHEDULE:
 Start Construction: June 2010
 Construction Complete: Sept. 2010

UPCOMING ACTIVITIES :
  • Architect has begun planning and design work.  Construction will start in June of 2010 with completion scheduled for August of 2010.

 

PROJECT PHOTOS:
     

  Riverside Elementary Boiler Replacement:

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Dan Golden
 Architect:  
 Contractor:  
 Engineer:  SDC

PROJECT SCHEDULE:
 Start Construction:  June 25, 2007
 Construction Complete:  August 31, 2007
UPCOMING ACTIVITIES :
  • Complete

PROJECT PHOTOS:
     

Riverside Elementary School Roofing Project:

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager: Tony Walters, Milestead & Associates
 Architect:  BB&L
 Contractor:  McDonald, Snyder, ABC Griffith
 Engineer:  N/A

PROJECT SCHEDULE:
 Start Construction: June 20, 2007
 Construction Complete:  August 31, 2007

UPCOMING ACTIVITIES :
  • Complete
 
PROJECT PHOTOS: