Riverside Elementary


Last Updated on 7-15-10

PROJECT SUMMARY:

 There are three projects at Riverside Elementary:

1.   Building Improvements
2.   Boiler Replacement
3.   Roofing Project
 
 Riverside Elementary School Building Improvements:
PROJECT SUMMARY:

Bond funded improvements at Riverside Elementary are scheduled for the summer of 2010.  Work will include: interior painting,  replacement of most classroom windows, flooring replacement in selected classrooms, repairs to covered play area, play equipment area drainage, upgrades to clock system, and pavement upgrades.

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Joanna Evenson, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates and Lee
 Contractor:  Skyward Construction
 Engineer:  HHPR


PROJECT SCHEDULE:
 Start Construction: June 2010
 Construction Complete: Sept. 2010

UPCOMING ACTIVITIES :

  • Skyward Construction started work on June 21st. Asbestos tile removal has been completed. Old windows have been removed. Old, rotted exterior on the covered play area has been removed.
  • Work on window replacement, pavement upgrades in the play area, new metal exterior siding on the covered play area, new clocks, ceiling upgrades in the hallways, door hardware upgrades, and interior painting have all started and will be completed by August 28th.
  • Work has also started on play equipment area improvements and expansion. 

 

PROJECT PHOTOS:
     

  Riverside Elementary Boiler Replacement:

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Dan Golden
 Architect:  
 Contractor:  
 Engineer:  SDC

PROJECT SCHEDULE:
 Start Construction:  June 25, 2007
 Construction Complete:  August 31, 2007
UPCOMING ACTIVITIES :
  • Complete

PROJECT PHOTOS:
     

Riverside Elementary School Roofing Project:

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager: Tony Walters, Milestead & Associates
 Architect:  BB&L
 Contractor:  McDonald, Snyder, ABC Griffith
 Engineer:  N/A

PROJECT SCHEDULE:
 Start Construction: June 20, 2007
 Construction Complete:  August 31, 2007

UPCOMING ACTIVITIES :
  • Complete
 
PROJECT PHOTOS: