PROJECT SUMMARY:
Emerick Construction completed an extensive remodel of Rowe Middle School in March, 2009. The following items are included in the project:
  • Expansion of the gym by 50% to create a full size middle school gym. This work included installation of folding bleachers that will accommodate seating of the entire 750 student population.
  • Expanded and remodeled lobby and new entry to the office
  • Complete remodel of the locker rooms
  • New choir room
  • Students lockers were replaced
  • Exterior and Interior painting
  • Replacement of chalk boards with dry marker boards
  • Installation of air conditioning for the counseling center
  • Elevator to the upper gym to create ADA access
  • Fire Sprinkling of the entire building and removal of hallway doors to increase visibility and safety
  • Upgrades of flooring, heating units, dry marker boards, lockers, and interior painting
  • New bus drop off, walkways to Lake Road along the bus access lane, improved parent drop off, and additional parking
  • Work on the interior renovations was completed in August, 2008. Work on the gym and choir room were completed in March, 2009.
SUMMER OF 2009 THE FOLLOWING WORK WAS COMPLETED:
  • Old floor tile in the halls and classrooms replaced
  • Remaining 14 classroom heating units replaced
  • Flooring in the upper gym will be upgraded
  • Kitchen remodeled.
  • Air Conditioning added to Computer Lab
    Elevation      Plans

PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas School District
 Project Manager:  Craig Markus, Cornerstone Management Group
 Architect:  Mahlulm Architects
 Contractor:  Emerick Construction

 
PROJECT SCHEDULE:
 Construction Start: June 16, 2008 
 Move In Date: August 15, 2009 
 Completion Date: August 31, 2009 
 

UPCOMING ACTIVITIES:

  • All Bond Funded Work Completed

PROJECT PHOTOS:

 
Kitchen 8/09 Kitchen 8/09
Kitchen 8/09 Kitchen 8/09
Kitchen: Duct Work 8/09 Kitchen 8/09
Kitchen 8/09 New Kitchen Floor 8/09
Kitchen 8/09 Kitchen: Trench Filled  8/09
Walk in Freezer 7/09
Sheet Rock in Kitchen 7/09
New Flooring 7/09 New Flooring 7/09
Kitchen 7/09
Kitchen 7/09
KItchen 7/09 Kitchen 7/09
Kitchen 7/09 Hall 7/09
 Cafeteria 7/09
New Wood Floor in Upper Gym 7/09
Rowe Lobby and Gym 4/09 Rowe Lobby and Gym 4/09
Rowe Lobby and Gym 4/09 New Main Office Windows 4/09
Office Remodel 3/09 Office Remodel 3/09
New Lockers 3/09 New Lights by Kitchen 3/09
 New Bleachers in New Gym Addition 3/09
New Gym Addition 3/09
Hallway Leading to New Gym Addition 3/09
New Gym Floor Installation 3/09
 Gym Preparing for New Wood Floor 2/09
Front Lobby: Emerick PM, Eric Smith and
Site Superintendent, Carlo.
New Gym Addition 2/09 New Choral Room 2/09
Fine Arts Front Site Work 1/09 Fine Arts Make Up Room 1/09
Rowe Gym Addition 1/09 Rowe Gym Addition 1/09
Exterior Painting on Gym Addition 1/09
Interior Gym Addition Work 1/09
Rowe Middle School from Street 1/09 Corridor with partions removed 1/09
 
 New Lockers 1/09
Rowe bus loop side of gym addition exterior 12/08
Rowe gym new gym addition interior12/08 Rowe front lobby and gym addition exterior 12/08
Rowe Gym 12/08 Rowe Gym 12/08
Rowe Gym 12/08 Rowe Gym 12/08
Front Lobby Interior 11/08 Exterior View of Front Lobby and Gym Addition 11/08
Tilt up Panels 11/08 Front Lobby 11/08
Gym Addition 11/08
Rowe Front Lobby and Gym Addition 11/08
 Rowe Gym Addition from Lake Rd. 11/08
Gym Addition 10/08
Front Lobby 10/08 Front Lobby 10/08
Rowe Gym Addition Tilt Panels 10/08 Rowe New Front Lobby 10/08

Tile Panel Formwork on New Gym Slab Addition 9/08

 

Front Lobby 9/08
Support for gym, bus loop paved Front lobby slab preparation
   

Pouring  Sheer Wall Putting Bridge Truss Together

Steel Support for Bridge Tress 8/08



Interior Painting 8/08

New Lights in Classroom 8/08

Bus Loop 7/08

Bus Loop 7/08

Bus Loop

Front of Building

 

  Gym Panel Removal 7/08

 Front Lobby 7/08