Sojourner School New


Last Updated on 7-15-10
  Elevation      Plans





PROJECT SUMMARY:
Upgrades and renovation activities will start in the summer of 2010.  Work includes replacement of classroom sinks and counter tops, new white boards, new window coverings, replacement of flooring in multi-purpose room, upgrade of fire alarm, new covered play structure, upgrade of play equipment area, improved bus loading area.

PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, Clackamas School District
 Project Manager:  Joanna Evenson, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates & Lee
 Contractor:  Skyward Construction

 
PROJECT SCHEDULE:
 Construction Start:
 June 2010
 Construction Complete
August 2010 
 
Upcoming Events:
  • Skyward Construction started work on June 21st
  • Asbestos abatement of floor tile in the multi-purpose room has been complete
  • Interior demolition in the areas of the rest room and classroom sink replacement is underway. New counter tops are being installed. 
  • Rest room remodel is progress with rough in plumbing nearing completion.
  • Excavation for footings for the new covered play area has started.