Spring Mountain Elementary


Last Updated on 4-1-09

PROJECT SUMMARY:
Summary coming soon.



PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas School District
 Project Manager:  Jon Sandstrom, J.J. Henri Co., Inc.
 Architect:  N/A
 Contractor:  TBD
 Engineer: N/A

 
PROJECT SCHEDULE:
 Construction Start:  June ,2008
 Completion Date:  September, 2008
 

UPCOMING ACTIVITIES:
  • Roofing of classroom areas
  • Mechanical, electrical, & plumbing rough in
  • Masonry veneer ongoing
  • Painting in gym
  • Sewer line on 172nd Avenue has been completed
  • Paving 172nd Avenue

PROJECT PHOTOS:

   

Playground w/New Chips and Rubberized Matt

 Sound Barrier in Media Center
 Framing Detail