Summary of Building Projects

PROJECT DESCRIPTION

STATUS

MILWAUKIE HIGH ATTENDANCE AREA

 

Milwaukie High School

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Paint entire schoool exterior  Complete
Replace roof- 1980 main bldg and industrial arts bldg  Complete
Replace roof-1982 section of gym building  Complete
Exterior stucco restoration  Complete
Renovate 1984 auditorium roof  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Renovate girls locker room heat and ventilation  Complete
Replace two 1949 boilers  Complete
Replace all building steam traps  Complete
Renovate heating system thermostats/ control valves  Complete
Convert heating controls to direct digital system  Complete
Replace all classroom unit ventilators(heating)  
Renovate media center heat/vent system  Complete
Renovate photo copy room heat/vent system  Complete
Replace 1971 auditorium boiler  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  Complete
Replace 1963 football field lights and poles  Complete
Upgrade lighting in all areas not previsously completed  Complete
Replace 1975 master intercom paging unit and wiring  Complete
Replace 1960 master clock system  Complete
Replace obsolete stage lighting instruments  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace chalkboards and tackboards  Complete
Replace and upgrade exterior door hardware  Complete
Wrestling room floor replacement  Complete
Clean, replace or repair stage curtains  Complete
Interior finish renovation of the Fine Arts Building  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Repair drainage on Lake Road athletic field  Complete
Re-pave Lake Road parking lot  Complete
Construct storage building on main field  Complete
Facility Improvements (major renovation and repair of aging facilties)  
Gym rest room improvements for disabled access  Complete
Renovate rest rooms in the Art/Tech area  Complete
Renovate upper and lower girls locker rooms  Complete
Provide disabled access to Fine Arts Building  Complete
Provide improved facilities for band, drama, and dance  Complete
   
Back to Top

 

Rowe Middle School

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  Cmplete
Exterior siding and roof horiz. trim board renovation  Complete
Paint entire school exterior  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace all unit ventilators in 1963 portion of bldg.  Complete
Convert heating controls to direct digital system  Complete
Upgrade ventilation in upper gym  Complete
Plumbing fixture renovation in older section rest rooms  Complete
Heat/Vent improvements for counseling office  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade and replace lighting throughout  Complete
Replace and upgrade lighting in old locker rooms  Complete
Replace obsolete dimming equipment on stage  Complete
Install sound system in gym  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards  Complete
Paint the entire interior of the building  Complete
Replace and upgrade corridor lockers  Complete
Corridor wall finish and tackboard upgrade  Complete
Acoustic treatment for main and upper gyms  Complete
Repair and upgrade exterior door hardware  Complete
Install locks on all rest room doors  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Extend west driveway sidewalk to Lake Road  Complete
Overlay paving behind gym and shop  
Add additional parking on the site  Complete
Construct walkway to Licyntra Dr.(City requirement)  Complete
Construct running track  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Construct additional staff rest rooms  Complete
Construct additional gym and locker room space.  Complete
Construct choral music room  Complete
Renovate Front Entrance  Complete
Remodel existing locker rooms  Complete
Renovate kitchen  Complete
Install corridor gates for night security and safety  Complete
   
Back to Top

 

Ardenwald Elementary

 
Replace Building on site  Complete
   
Back to Top

 

Campbell Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace rotted windows/walls in south facing units  Complete
Replace exterior doors and hardware  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace worn out classroom furnaces (total 7)  Complete
Replace boiler in Unit A  Complete
Renovate and upgrade plumbing fixtures in all rest rooms  Complete
Install drinking fountains in corridors  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade exterior lighting  Complete
Replace 1975 intercom and clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Paint entire interior of the building  Complete
Replace worn out carpet/flooring throughout building  Complete
Replace sinks/countertops in all classrooms  Complete
Renovate interior finishes and paint the main office  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Repair concrete courtyards and paved walkways  Complete
Renovate upper playground  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Install air conditioning in the computer lab  Complete
Renovate kitchen  Complete
Fill in the stage opening with a permanent wall  Complete
Install bleachers in the gym  Complete
   
Back to Top

 

Lewelling Elementary

 
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Convert heating controls to direct digital system  Complete
Renovate rest room fixtures  Complete
Replace all classroom sinks  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Renovate and upgrade lighting throughout  Complete
Replace intercom and clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out floor tile throughout entire building  Complete
Replace worn out chalkboards and add tackboards  Complete
Renovate interior corridor wall surfaces with tackboard  Complete
Replace all door hardware and closers  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Landscaping renovation and improvements  Complete
Construct paved walkway to Willow Street  Complete
Resurface tennis courts  Complete
Construct paved jogging path  Complete
Overlay deteriorated play area asphalt paving  Complete
Extend sidewalk at gym overhang by parking area  Complete
Expand irrigation system to central courtyards  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Expand and improve office facilities  Complete
Renovate rest room finishes throughout building  Complete
Renovate kitchen  Complete
Add folding bleachers to the gym  Complete
   
Back to Top

 

Linwood Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Weatherize the windows  Complete
Paint the entire exterior of the building  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Repair and renovate 1968 heating system components  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Replace 1980 intercom and 1968 clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Paint the entire interior of the building  Complete
Replace worn out chalkboards and add tackboards  Complete
Replace window coverings  Complete
Renovate interior finish of the main corridor  Complete
Replace worn carpeting in 8 classrooms and open areas  Complete
Upgrade and repair exterior door hardware  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Install drainage improvement in the playground area  Complete
Overlay paving in the parking lot  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Media Center addition per the master plan  Complete
Gym addition per the master plan  Complete
Renovate rest room interior finishes and equipment  Complete
Renovate kitchen and loading and access  Complete
Renovate and reconfigure the office area  Complete
   
Back to Top

 

Milwaukie Elementary/El Puente

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace the 1981 flat section of the roof  Complete
Replace the remaining wood/metal windows  Complete
Replace exterior doors and hardware  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
General upgrade and renovation of old steam heat system  Complete
Upgrade ventilation and heat in multi-purpose room  Complete
Replace all classroom sinks  Complete
Add sinks in four north classrooms  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Improve parking lot security lighting  Complete
Improve lighting under covered play area  Complete
Replace 1978 intercom and clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Paint covered play area ceiling  Complete
Replace stage curtains  Complete
Replace worn out chalkboards and tackboards  In Progress
Replace window coverings in all rooms  In Progress
Replace the orginal 1935 wood gym floor  Complete
Replace worn flooring throughout the building  Complete
Replace worn carpet floors in two classrooms  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Upgrade play equipment and play area drainage  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Renovate and expand main office  Complete
Install glass in all classroom doors  Complete
   
Back to Top

 

Whitcomb Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace windows and doors and weather strip  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Convert heating controls to direct digital system  Complete
Renovate 1958 building heating system and coils  Complete
Provide heat and ventilation to music rooms  Complete
Replace all classroom sinks  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade and replace lighting throughout  Complete
Replace 1982 intercom and clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Flameproof stage curtains  Complete
Replace worn out chalkboards and tackboards  Complete
Complete interior finishes renovation  Complete
Replace worn out folding wall on stage  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Install drainage along east side courtyards  Complete
Repair expansion joints in all concrete patios  Complete
Make repairs to the covered play area, lights paving etc.  Complete
Install drainage for the playground equipment  Complete
Overlay pave east driveway and fire lane  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Upgrade all rest rooms  Complete
Renovate kitchen and serving line  Complete
Install bleachers in the gym  Complete
   
Back to Top

 

Wichita Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace windows throughout building  
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Install ventilation for offices  
Renovate or replace all steam traps  
Replace radiators with vent fan heat units throughout  
Convert heating controls to direct digital system  
Replace all classroom sinks  
Replace cafeteria hand washing sink  
Improve ventilation in south facing classrooms  
Improve ventilation for the computer lab in basement  
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade the gym PA system  
Replace 1975 intercom and clock system  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace stage curtains  
Replace worn out chalkboards and tackboards  
Replace and upgrade classroom window coverings  
Paint the entire interior of the building  
Add acoustic wall treatment in gym  
Renovate gym floor  
Replace worn out floor covering throughout building  
Upgrade and repair exterior door hardware  
Grounds and Site Improvements (paving, landscaping, site structures)  
Renovate parking and bus loading areas  
Facillity Improvements (major renovation and repair of aging facilties)  
Covered play area expansion  
Renovate kitchen  
Renovate and reconfigure the office area  
   
Back to Top

 

REX PUTNAM HIGH ATTENDANCE AREA

 

Rex Putnam High School

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Paint the entire exterior of the building  Scheduled for 2010
Upgrade windows for energy efficieny and comfort  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Upgrade heating and cooling controls in Career Center  Complete
Convert heating controls to direct digital system  Complete
Replace heat unit ventilators in all the perimeter classrooms  Complete
Renovate wrestling room heat/ventilation system  Complete
Repair main gym flooring at drinking fountains  Complete
Replace deteriorated gas piping to science rooms  Complete
Replace drinking fountains throughout building  Complete
Reinsulate all trench and tunnel piping  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Replace 1967 football field lights and poles  Complete
Exterior lighting upgrade  Complete
Replace obsolete electrical panels  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards  Complete
Replace countertops in all classrooms  Complete
Paint entire interior and renovate all and tackboard surfaces  Complete
Replace original 1963 corridor lockers  Complete
Renovate the corridors with new tackboards and finishes  Complete
Replace wrestling room wall padding  Complete
Replace worn out flooring throughout the entire building  Complete
Sand and seal upper gym floor  Complete
Replace obsolete door hardware and doors  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Major repair to stadium structure and bleachers  Complete
Renovate and improve front courtyard  Complete
Renovate and improve central courtyard  Complete
Terrace and landscape east bank  Complete
Drill well and connect to field irrigation systems  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Renovate the cafeteria and the kitchen. Enlarge to a commons area with adequate capacity  Complete
Enlarge and reconfigure main front office and entrance  Complete
Renovate rest rooms throughout building  Complete
Construct stairs and lift to auditorium storage area  Complete
Science room renovation (6 rooms total)  Complete
Media Center Upgrades and Renovations  Complete
   
Back to Top

 

Alder Creek Middle School

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Paint the entire exterior of the building  
Replace and upgrade exterior doors and hardware  
Replace windows in classrooms  
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Renovate heat/ventilation in support services offices  
Repair and/or upgrade all steam traps  
Renovate or replace all steam control valves  
Replace 1957 heat/vent units in perimeter classrooms  
Renovate or upgrade 1957 heating units in the gym  
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Renovate and upgrade lighting in locker rooms  
Upgrade 1977 clock and intercom system  
Replace parking lot lighting poles and fixtures  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out floor covering in all areas of the buildling not done in 2001  
Renovate wall surfaces in three south cross corridors  
Correct tackboard "dimpling" problem  
Replace flooring in south corridor rooms  
Sink/counter replacement - three science rooms  
Replace PE lockers.  
Grounds and Site Improvements (paving, landscaping, site structures)  
Facillity Improvements (major renovation and repair of aging facilties)  
Construct entrance vestibule at the main office area  
Renovate all of the rest rooms in the entire building  
Renovate and repair south wing classrooms  
Add skylights for common areas per original plans  
Construct rest rooms for gym use and "E" corridor  
Kitchen renovation  
   
Back to Top

 

Bilquist Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  Complete
Repair and paint west wall of old covered play area  Complete
Replace exterior windows with energy efficient  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Upgrade ventilation in the old gym/cafeteria
 Complete
Upgrade rest room ventilation throughout  Complete
Convert heating controls to direct digital system  Complete
Replace all classroom heat/vent units  Complete
Replace plumbing fixtures in all rest rooms  Complete
Replace all classroom sinks  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Replace 1978 intercom and clock system  Complete
Improve site lighting  Complete
Renovate and upgrade light fixtures throughout  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards  Complete
Replace stage curtains  Complete
Replace media center circulation desk  Complete
Complete interior finish renovation and wood refinishing  Complete
Renovate corridor wall surfaces and display areas  Complete
Replace worn out floor coverings throughout building  Complete
Replace the worn out carpet in library and office  Complete
Upgrade and repair exterior door hardware  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Grade and reseed the upper playground area  Complete
Paving overlay for all hard surface play areas  Complete
Improve drainage and pavement on upper play area  Complete
Pave and renovate gravel parking and drop off zone  Complete
Improve parking lot and entrance signage  Complete
Facility Improvements (major renovation and repair of aging faciltiies)  
Renovate kitchen  Complete
Office and staff room renovation and expansion  Complete
General Renovations  Complete
Install bleachers in the gym  Complete
Replacement School Facilities  Complete
   
Back to Top

 

Concord Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace eight exterior door sets  
Replace the windows in the gym  
Replace north facing classroom windows  
Replace the 1977 roof on the east side of the building  
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace heat/vent units and radiators throughout building  
Replace both 1936 orginal boilers  
Renovate and upgrade steam traps  
Convert heating controls to direct digital system  
Replace all classroom and service sinks  
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade site lighting  
Upgrade and replace lighting throughout  
Replace 1976 intercom and clock system  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace stage curtains  
Replace worn out chalkboards and tackboards  
Classroom cabinet renovation  
Add tackboard surfaces for interior corridor walls  
Paint the interior of the entire building  
Renovate and restore gym floor  
Upgrade and repair exterior door hardware  
Grounds and Site Improvements (paving, landscaping, site structures)  
Replace deteriorating rock retaining wall  
Renovate siding of covered play  
General improvement and repairs to fields-drainage  
Renovate and repair the north parking lot  
Replace bad sidewalk around the building  
Facillity Improvements (major renovation and repair of aging facilties)  
Install gates to secure gym for night and weekend use  
Expand computer lab  
Renovate kitchen and cafeteria  
Office area renovation and reconfigure  
   
Back to Top

 

Oak Grove Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Repair and replace the 1979 old building roof  
Install sun screens on south facing classrooms  
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace sinks in all older building classrooms  
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade and replace lighting in older section  
Add electrical outlets in new wing classrooms  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards  Tackboard Done 2009
Add tackable material to folding walls  
Paint gym interior due to wall damage  
Paint classroom interiors of older section of building  
Grounds and Site Improvements (paving, landscaping, site structures)  
Landscaping on south side for heat and noise control  
Construct parking lot exit to Courtney Ave.  Complete
Renovate and enlarge playground equipment area  
Install underground irrigation system  
Facillity Improvements (major renovation and repair of aging facilties)  
Renovate four older section rest rooms  
Renovate the kitchen and cafeteria including flooring  
Enlarge covered play area  
Install folding bleachers in the gym  
   
Back to Top

 

Riverside Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace all windows( west side is priority)  
Replace 1977 roof over the south end of the building  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace both 1955 boilers  Complete
Replace all classroom sinks  
Replace fixtures in all rest rooms  
Convert heating controls to direct digital system  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade and renovate lighting throughout  
Replace 1980 intercom and clock system  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out flooring throughout entire building  
Replace worn out chalkboards and tackboards  
Provide acoustic treatment for older hallway ceilings  
Replace doors and hardware on entire building  
Grounds and Site Improvements (paving, landscaping, site structures)  
Replace rotted wood siding on covered play area  
Overlay all playground paving  
   
Back to Top

 

View Acres Elementary

 
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Add sink and plumbing in staff room  Complete
Convert heating controls to direct digital system  Complete
Renovate library/tech center and add ventilation  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade and replace lighting throughout  Complete
Replace 1982 intercom and clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards  Complete
Add acoustic treatment to cafeteria walls  Complete
Replace worn out tile floors throughout building Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Reconfigure parking lot for improved parent drop-off  Complete
Replace rotted wood siding on covered play area  Complete
Construct stairway to the lower play field.  Complete
Renovate upper playground and add drainage  Complete
Replace play structure/renovate play surface grounds  Complete
Overlay and pave exit drive to Hill Road  Complete
Renovate Hill road access to lower field  Complete
Construct larger covered play area expansion  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Rest room finish renovationa nd upgrade  Complete
Add skylights to three interior rooms  Complete
Renovate/expand or reconfigure office area  Scheduled for 2010
Move technology room to room 19 and add power  Complete
Renovate unused inner locker room to orchestra room  Complete
   
Back to Top

 

CLACKAMAS HIGH ATTENDANCE AREA

 

Clackamas High School

 
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Upgrade ventilation system in the Art Room  
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Additional tackboards in all corridors and classrooms  
Grounds and Site Improvements (paving, landscaping, site structures)  
Install drainage on practice soccer and football fields  
Facillity Improvements (major renovation and repair of aging facilties)  
Install stage lighting controls in black box theatre  
   
Back to Top

 

Sunrise Middle School

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Paint the entire exterior of the building  
Replace or renovate problem areas of building roof  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Convert heating controls to direct digital system  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Paint the entire interior of the building  
Replace rusted toilet partitions throughout building  
Replace worn out flooring in corridors and cafeteria  Complete
Replace worn out flooring in all classrooms and offices  
   
Back to Top

 

Clackamas Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace and renovate 1978 roof on main building  Complete
Replace windows in the annex  Complete
Repair bad stucco at front entrance  Complete
Replace and renovate 1979 roof on annex building  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace heat/vent units and radiators - entire building  Complete
Connect main building downspouts to storm drain  Complete
Upgrade and replace steam traps throughout building  Complete
Convert heating controls to direct digital system  Complete
Replace all classroom sinks  Complete
Ventilation improvements for main computer lab  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade site and entry lighting  Complete
Renovate and upgrade lighting throughout  Complete
Install underground electrical service  Complete
Replace 1975 clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards/room & halls  Complete
Replace window coverings throughout  Complete
Paint the interior of the entire building  Complete
Upgrade and repair exterior door hardware  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Renovate and improve parking around the building  Complete
Replace deteriorated sidewalks around entire site  Complete
Play area paving overlay  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Upgrade storage and shelving throughout school  Complete
Construct small meeting room  Complete
Renovate lower building rest rooms  Complete
Renovate unused storage room to office/conf. space  Complete
   
Back to Top

 

Scouters Mountain Elementary / Happy Valley Middle School

 
Replace Happy Valley Elementary School  Complete
Construct Happy Valley Middle School  Complete
   
Back to Top

 

Mount Scott Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Repair all dry rotted windows  Complete
Replace all exterior siding and paint the entire building  Complete
Replace 1989 shingle roof and gutters  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace obsolete heat control system  Complete
Replace 18 original 1989 classroom furnaces  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade lights to T-8 and electronic ballasts  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace rusted toilet partitions  Complete
Paint the interior of the entire building  Complete
Convert all chalkboards to dry marker boards  Complete
Sand and seal the gym floor  Complete
Replace deteriorating wood section of cafeteria floor  Complete
Replace worn floor covering on stairwells and lower level  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Add drainage to play field  Complete
Expand the covered play area  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Install TV wall mounts in all rooms  Complete
Install volleyball standard system in the main gym  Complete
   
Back to Top

 

Oregon Trail Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Repair and re-roof sections as needed.  Complete
Replace leaking classroom doors  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)
Replace obsolete heat control system  Complete
Improve ventilation to the computer center classroom  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Paint the interior of the entire building  Complete
Sand and seal the gym floor  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Renovate and add drainage to playground area  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Expand the cafeteria, add computer lab and conf. room  Complete
Incorporate conference room into future construction  Complete
   
Back to Top

 

Spring Mountain Elementary

 
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Upgrade ventilation system controls  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Cover concrete stairs with rubber tread material  Complete
Acoustic treatment for library, gym, cafeteria  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
   
Back to Top

 

Sunnyside Elementary

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Renovate and replace the 1974 Unit B roof area  Complete
Replace Unit A windows  Complete
Replace rotted vertical cedar siding on units C and D  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Convert heating controls to direct digital system  Complete
Replace 1960 Unit B boiler  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade electric system in library and computer rooms  Complete
Replace 1981 intercom and clock system  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards  Complete
Paint the interior of the entire building  Complete
Replace worn out floor covering in Unit B  Complete
Sand and seal gym floor  Complete
Renovate wall finish and fixtures unit A rest rooms  Complete
Upgrade and repair exterior door hardware  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Overlay paving for all play areas  Complete
Install drainage system on the play field  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Renovate rest room wall finishes in sectors B and C  Complete
   

New School Facilties

 
Construct Elementary Schools  
Construct Elementary  School    
Construct Middle School  
   
Back to Top

 

DISTRICT FACILITIES

 

Sojourner School/New Urban High School

 
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace all classrooms sinks/countertops  
Repair and upgrade hallway drinking fountains  
Install separate water heater for annex building  
Relocate control compressor for noise abatement  
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Replace intercom and clock system  
Upgrade fire alarm system  
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Replace worn out chalkboards and tackboards  
Replace window coverings in all rooms  
Repair and Upgrade hall way tackboard/display areas  
Replace the floor in the mult-purpose room  
Grounds and Site Improvements (paving, landscaping, site structures)  
Upgrade and improve play area  
Overlay pave the asphalt play area  
Repair and upgrade west bus loading area  
Facillity Improvements (major renovation and repair of aging facilties)  
Renovate rest room wall finishes and fixtures  
Construct covered play area structure  
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Replace and renovate the 1978 roof  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Replace all worn out 1930's unit ventilators and radiators  
Insulate steam pipes to annex building  
Upgrade all water piping systems  
Repair and replace all steam traps  
Replace obsolete heat control system  
Replace all rest room sinks and fixtures  
Grounds and Site Improvements (paving, landscaping, site structures)  
Pave and improve parking and loading areas  
   
Back to Top

 

Sabin/Schellenberg - North

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Renovate exterior finish of all campus buildings  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Convert heating controls to direct digital system  Complete
Replace all gas unit heaters  Complete
Renovate heating systems in teen parent and Child Services  Complete
Install oil/water separator in auto shop  Complete
Renovate the greenhouse covers and heating system  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade and improve exterior site lighting  Complete
Replace 1968 clock system  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Parking and bus driveway improvements  Complete
Pave gravel parking and overlay all paved areas  Complete
Facillity Improvements (major renovation and repair of aging facilties)  
Renovate building to accommodate new/expanded programs  Complete
Renovate all rest rooms  Complete
   
Back to Top

 

Sabin/Schellenberg - South

 
Building Envelope (roofing, siding, exterior painting, windows, etc.)  
Paint the entire exterior of the building  Complete
Mechanical Systems (heating, ventilating, air conditioning, plumbing, controls, etc.)  
Convert heating controls to direct digital system  Complete
Replace heat/vent units throughout the building  Complete
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Upgrade the fire alarm system to current code  Complete
General Building Maintenance (ceilings, floors, structure, interior finishes)  
Refinish all interior doors  Complete
Grounds and Site Improvements (paving, landscaping, site structures)  
Pave and overlay all parking lots and paved areas  Complete
Complete the connections to storm drain system  Complete
   
Back to Top

 

Administration Building

 
Facillity Improvements (major renovation and repair of aging facilties)  
20,000 s.f. addition to consolidate facilities  
   
Back to Top

 

Physical Plant Site

 
Facillity Improvements (major renovation and repair of aging facilties)  
General renovation, parking and ADA improvements  
   
Back to Top

 

Transportation Center

 
Facillity Improvements (major renovation and repair of aging facilties)  
Replacement of Transportation Center  
   
Back to Top

 

District Sports Facilities

 
Grounds and Site Improvements (paving, landscaping, site structures)  
Clackamas High School Field Turf  Complete
Milwaukie High School Field Turf/Track  Complete
Rex Putnam High School Field Turf/Track  Complete
   
   
Back to Top

 

TECHNOLOGY

 

District Facilities and Sites

 
Computers, Data Networking, communications  
   
Back to Top

 

INFRASTRUCTURE

 

District Facilities and Sites

 
Electrical Systems (power, lighting, communications, burglar and fire alarms)  
Security System/Card Key - Districtwide  
Fire alarm upgrade - Districtwide  
MHS, Sabin, Sunrise, Rowe, Alder Creek, Campbell  
Clackamas El, Concord, Lewelling, Linwood, Riverside  
Sunnyside, View Acres, Whitcomb, Wichita  
Alder Creek - Replace field lighting poles and underground service  Complete
Upgrade clock and bell systems - district wide  
Grounds and Site Improvements (paving, landscaping, site structures)  
Install safety cushion on all elementary play equipment  
District-wide anti-skateboarding measures  
Facillity Improvements (major renovation and repair of aging facilties)  
   
Back to Top

 

LAND PURCHASE

 

New School Facilties

 
Six Properties - 80 to 100 acres of land:  
Happy Valley School(s) Site  Complete
New Elementary School Site  Complete
New Elementary School Site  Complete
New Middle School Site  Complete
Future Vogel Site  Complete
Future Site