Sunrise Middle School


Last Updated on 4-14-11


PROJECT SUMMARY:
There are three projects at the Sunrise Middle School:
1. Building Improvements
2. Flooring Upgrades
3. Roofing Project

 
Building Improvements:

PROJECT SUMMARY:
Building Improvements will be performed during the summer of 2010 as part of the work to convert Sunrise Middle School into Clackamas High School East Campus.  Work included replacing all classroom flooring, interior painting and wall finish upgrades, roofing, exterior painting, construction of a covered walk connecting Clackamas High School and Sunrise, converting a portion of the east gym to a weight room and renovation of the old shop area to a dance studio.


PROJECT TEAM:

Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Joanna Evenson, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates & Lee
 Contractor:  JE dunn
 Engineer:  HHPR
 
PROJECT SCHEDULE:
 Start Construction: June 2010
 Construction Complete: Sept. 27, 2010

UPCOMING ACTIVITIES:
  • All work on the project was completed in October 2010 by JE Dunn Construction.
  • Flooring Upgrades - Hallways

PROJECT PHOTOS:
 
Front Entrance 10/10 Front Office 10/10 Weight Room 10/10
Cafeteria 10/10 Cafeteria 10/10 Mural 10/10
Cafeteria Wash Station 10/10 Dance Studio 10/10 Lecture Room 10/10
Main Hallway 10/10
Media Center 10/10
Media Center 10/10
Walkway from East Campus 10/10 Walkway from West Campus 10/10 Remodeled Restrooms 10/10
   
Classroom Hallway 10/10    

  

Boiler Replacement:


PROJECT SUMMARY:
Boiler Replacement was completed during the Summer of 2007

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Dan Golden
 Engineer:  SDC

PROJECT SCHEDULE:
 Start Construction:  June 25, 2007
 Construction Complete:  August 31, 2007
UPCOMING ACTIVITIES :
  • Complete

Roofing Project:

PROJECT SUMMARY: The Sunrise Middle School received a new metal roof during the Summer of 2007

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager: Tony Walters, Milestead & Associates
 Architect:  BB&L
 Contractor:  McDonald, Snyder, ABC Griffith
 Engineer:  N/A

PROJECT SCHEDULE:
 Start Construction: June 20, 2007
 Construction Complete:  August 31, 2007

UPCOMING ACTIVITIES :
  • Complete