Sunrise Middle School


Last Updated on 4-21-10


PROJECT SUMMARY:
There are three projects at the Sunrise Middle School:
1. Building Improvements
2. Boiler Replacement
3. Roofing Project

 
Building Improvements:

PROJECT SUMMARY:
Building Improvements will be performed during the summer of 2010 as part of the work to convert Sunrise Middle School into Clackamas High School East Campus.  Work includes replacing all classroom flooring, interior painting and wall finish upgrades, roofing, exterior painting, construction of a covered walk connecting Clackamas High School and Sunrise, converting a portion of the east gym to a weight room and renovation of the old shop area to a dance studio.


PROJECT TEAM:

Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates & Lee
 Contractor:  TBD
 Engineer:  TBD

PROJECT SCHEDULE:
 Start Construction: June 2010
 Construction Complete: Sept. 27, 2010

UPCOMING ACTIVITIES:
  • Bids have been received and a recommendation for award of contract is going to the District Board on May 6th.  Construction will start in June 2010 with completion scheduled for August 2010..

PROJECT PHOTOS:
     

  

Boiler Replacement:


PROJECT SUMMARY:
Boiler Replacement was completed during the Summer of 2007

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager:  Dan Golden
 Architect:  
 Contractor:  
 Engineer:  SDC

PROJECT SCHEDULE:
 Start Construction:  June 25, 2007
 Construction Complete:  August 31, 2007
UPCOMING ACTIVITIES :
  • Complete

PROJECT PHOTOS:
 


Roofing Project:

PROJECT SUMMARY: The Sunrise Middle School received a new metal roof during the Summer of 2007

PROJECT TEAM:
Capital Project Manager: Garry Kryszak, Clackamas School District
 Project Manager: Tony Walters, Milestead & Associates
 Architect:  BB&L
 Contractor:  McDonald, Snyder, ABC Griffith
 Engineer:  N/A

PROJECT SCHEDULE:
 Start Construction: June 20, 2007
 Construction Complete:  August 31, 2007

UPCOMING ACTIVITIES :
  • Complete

PROJECT PHOTOS: