Verne A. Duncan Elementary


Last Updated on 02-4-10

PROJECT SUMMARY:

The Verne A. Duncan Elementary School Project is being planned for construction on a 11 acre site just west of 172nd Avenue in Happy Valley at 14898 SE Parklane Drive. The new building will be approximately 62,000 SF.  The Elementary School (Kindergarten through 6th Grade) will accommodate 550 students. The new Elementary School opened in September 2009.


PROJECT TEAM:
Capital Project Manager:  Garry Kryszak, North Clackamas School District
 Project Manager:  Joanna Evenson, J.J. Henri Co., Inc.
 Architect:  Barrentine, Bates and Lee
 Contractor:  Triplett-Wellman

 
PROJECT SCHEDULE:
 Site Development Activities
July 2008 - Nov. 2008
Overall Construction Schedule: Aug. 2008 - Aug. 2009
 
PROJECT SCHEDULE 
 

 UPCOMING EVENTS:
  • Project completed in August 2009.
 
PROJECT TIME LAPSE VIDEO:

Launch in external player
 



PROJECT PHOTOS & RENDERINGS:
 
 
 
Aerial 6/09